Time Accuracy Report Card will calculate several totals for the work scheduled by the dispatchers for the selected date range.
Items are included based on the Work Order date (not the Feild Ticket date). Work not field ticketed will not be included.
Note: This reports values for the Lead Tech only (values from additional workers are excluded)
Run the Time Accuracy Report Card by going to Reports-> Report Cards->Time Accuracy Report Card-> Select Report Parameters